GGOS Milestones

Id... Milestone Description Target Date Date achieved
IS.. Implementation of GGOS Structure The milestones collected under this heading detail the steps towards full implementation of the GGOS Structure . .
IS01 CfP for new components issued Milestone: Four new entities, the Coordinating Office, the Bureau for Network and Communication, the Bureau for Standards and Conventions, and the Bureau for Satellite Missions, are to be established. Moreover, GGOS needs to develop and operate a GGOS Web Portal. A Call for Proposals for these four entities has to be prepared and made public in the IAG community. The Coordinating Office and the Web Portal are closely related and will be solictied in one CfP. A specifications for the GGOS Web Portal needs to be prepared and published.
Status: The Calls were issued and made public through the mailing lists of the IAG Services. For the CfPs, see http://ggos.gfz-potsdam.de/ggos/index.php?id=20 or the "Official Documents" page in the GGOS Library.
Contacts: For more information, contact Markus Rothacher.
07/2008 07/2008
IS02 CfP for IGFS Central Bureau issued Milestone: The IGFS plans to establish a Central Bureau. A Call for Proposals for this entity has to be prepared and made public in the IAG community.
Status: The status is currently unknown.
Contacts: For more information, contact Rene Forsberg.
07/2008 .
IS03 New GGOS components identified Milestone: Based on the proposals received in response to the CfP (Milestone IS01), the institutions/groups responsible for the implementation of the new components need to by identified.
Status: Only three proposals were received, one each for the Web Portal, the Bureau for Networks and Communication, and one for the Bureau for Standards and Conventions. No proposals were received for the Coordinating Office and the Bureau on Satellite Missions. The Proposals received have been evaluated by a panel of five evaluators, and decisions on the Bureau for Networks and Communication, the Bureau for Standards and Conventions, and the GGOS Web Portal operator are expected at the 14th Steering Committee Meeting on December 14, 2008 in San Francisco.
Contacts: For more information, contact Markus Rothacher.
12/2008 .
IS04 GGOS Portal Beta version established Milestone: A Beta Version of the GGOS We Portal needs to be established and made available for a test period. Test should be solicited by a large number of internal and external user groups, including the IAG Services, GEO Communities of Practice, and GEO Committees.
Status: The work on this milestone can start as soon as the operator of the Web Portal has been identified.
Contacts: tbd.
07/2009 .
. GGOS Portal operational Milestone: At the end of a successful test phase (see Milestone ISO4) including potential modifications and extensions, the GGOS Web Portal will be declared operational.
Status: Work not started.
Contacts: tbd.
12/2009 .
NC.. GGOS WG on Network and Communication Milestones related to network integration, colocation of techniques, and development of networks. . .
NC01 SLR/VLBI Network Study completed Milestone: A study of the network structure required for reaching specified accuracy levels has to be conducted as a basis for network planning.
Status: The study is currently under way and a number of preliminary results have been presented at various meetings.
Contacts: For more information, contact Erricos Pavlis.
12/2008 .
NC02 Network Study Report completed Milestone:
Status:
Contacts: For more information, contact .
. 06/2008 .
. Report on Ground Survey Study Group Milestone:
Status:
Contacts: For more information, contact .
12/2009 .
. Colocation Site Survey Data Base Milestone:
Status:
Contacts: For more information, contact .
03/2009 .
. Requirements and format for the Meteorological Data Base Milestone:
Status:
Contacts: For more information, contact .
04/2009 .
. Progress towards real-time access Milestone:
Status:
Contacts: For more information, contact .
12/2008 .
SC.. GGOS WG on Standards and Conventions The Milestones listed here are related to the development of geodetic standards and conventions and the conditons with respect to adherence to these standards and conventions. . .
ID.. GGOS WG on Infrastructure and Data The Milestones reported here are mainly releated the development of the data infrastructure, including the web portal, and interoperability issues. . .
UO GGOS WG on User Linkage and Outreach . . .
. GGOS WG on Satellite Missions . . .
. GGOS WG on GEO Relations . . .
. Science Panel . . .
. Activities and Projects . . .
AP01 GGOS 2020 Book in print . 12/2008 .
AP02 GGOS 2020 Book in published . 06/2009 .
AP03 IGCP 565 Project awarded . 03/2008 03/2008
AP04 IGCP 565 Project First Workshop . 12/2008 .
AP05 IGCP 565 Project Second Workshop . 10/2009 .
WM Workshops and Meetings . . .
WM01 2006 GGOS Retreat . 04/2006 04/2006
. 2006 GGOS Workshop . 10/2006 10/2006
. 2007 GGOS Retreat . 03/2007 03/2007
. 2007 GGOS Workshop . 11/2007 11/2007
. 2007 GGOS UNified Analysis Workshop . 12/2007 12/2007
. 2008 GGOS Retreat . 03/2008 03/2008
. 2009 GGOS Science Workshop . 07/2009 .
PU Publications . . .